- Last assessed visit
- Jun 2026
- Compliant
Visits from January 1, 2023 to July 6, 2026, the comparison window. Only visits that assessed compliance are counted; consultations are not. Open means issued, in progress or ongoing when the file was taken; the other counts cover every year.
About this home
Every visit on record
Newest first. A visit that found nothing says so. Each finding shows the standard it was cited under, when it was issued, the date by which it had to be fixed, and where it stands.
June 11, 2026 · Inspection
Compliant
May 15, 2025 · Inspection
Non-compliant
Continuation of Services — Practicability, communication and review of plans
Evidence required that the continuation of services plan is communicated and made available to resid
Issued May 15, 2025. Fix by June 16, 2025. Status: Rectified (May 15, 2025).
Concerns and Complaints — Written processes for managing concerns and complaints
Evidence required of communication of the written process to residents, their representatives, visit
Issued May 15, 2025. Fix by June 16, 2025. Status: Rectified (May 15, 2025).
October 20, 2023 · Inspection
Non-compliant
Continuation of Services — Practicability, communication and review of plans
Evidence required that the continuation of services plan is communicated and made available to resid
Issued October 20, 2023. Fix by November 30, 2023. Status: Rectified (October 20, 2023).
June 17, 2022 · CMOH Inspection
Compliant
June 17, 2022 · Inspection
Compliant
October 20, 2021 · CMOH Inspection
Compliant
October 20, 2021 · Inspection
Non-compliant
Maintenance Requirements — Accommodation is maintained
Evidence required that the accommodation, equipment and furnishings are well maintained and in good
Issued October 20, 2021. Fix by November 30, 2021. Status: Rectified (November 26, 2021).
Continuation of Services — Practicability, communication and review of plans
Evidence required that the continuation of services plan is communicated and made available to resid
Issued October 20, 2021. Fix by November 30, 2021. Status: Rectified (November 26, 2021).
April 7, 2020 · Consultation
Not assessed (consultation)
October 9, 2019 · Inspection
Non-compliant
Duties of an Operator — Provide Inspection Results
Provide evidence that information on inspection results have been provided to_x000D_ residents and their
Issued October 9, 2019. Fix by November 30, 2019. Status: Rectified (October 11, 2019).
October 9, 2019 · Inspection
Compliant
October 10, 2018 · Inspection
Non-compliant
Duties of an Operator — Provide Copies of Process to Address Requests and Concerns
Provide evidence that copies of the written process established under clause 5(f) are_x000D_ provided to
Issued October 10, 2018. Fix by November 30, 2018. Status: Rectified (November 22, 2018).
Establishment of a Resident and Family Council — Meeting Every 6 Months to Inform Residents
Provide evidence that a meeting has been convened to inform residents, their families and persons of
Issued October 10, 2018. Fix by November 30, 2018. Status: Rectified (November 26, 2018).
Duties of an Operator — Establish a Written Process for Addressing Concerns
Provide evidence that a written process is established for addressing requests and_x000D_ concerns of th
Issued October 10, 2018. Fix by November 30, 2018. Status: Rectified (November 22, 2018).
October 10, 2018 · Inspection
Non-compliant
Continuation of Services — Practicability, communication and review of plans
Evidence required that the continuation of services plan is communicated and made available to resid
Issued October 10, 2018. Fix by November 30, 2018. Status: Rectified (November 22, 2018).
Window Coverings — Appropriate window coverings
Evidence required that each resident room has adequate window coverings.
Issued October 10, 2018. Fix by November 30, 2018. Status: Rectified (November 27, 2018).
Maintenance Requirements — Accommodation is maintained
Evidence required that the accommodation, equipment and furnishings are well maintained and in good
Issued October 10, 2018. Fix by November 30, 2018. Status: Rectified (November 27, 2018).
October 19, 2017 · Inspection
Compliant
October 19, 2016 · Inspection
Compliant
October 1, 2015 · Inspection
Compliant
October 20, 2014 · Inspection
Compliant
October 16, 2013 · Inspection
Compliant
Questions to ask on a visit
Built from the standards this home was cited under, not from anything we found. Ask how it meets each one today.
- How does the home meet: Continuation of Services — Practicability, communication and review of plans?
- How does the home meet: Concerns and Complaints — Written processes for managing concerns and complaints?
- How does the home meet: Maintenance Requirements — Accommodation is maintained?
- How does the home meet: Duties of an Operator — Provide Inspection Results?
- How does the home meet: Duties of an Operator — Provide Copies of Process to Address Requests and Concerns?
- How does the home meet: Establishment of a Resident and Family Council — Meeting Every 6 Months to Inform Residents?
Homes nearby
Straight-line distance between postal code centres (in rural Alberta, town centres). Each home’s share of non-compliant visits since 2023, on the same method as the city pages.
| Home | Type | Distance | Non-compliant |
|---|---|---|---|
| Villa St JosephBonnie Doon, Edmonton · 10 units | Supportive living | under 1 km | 100%1 of 1 visit |
| Iris CourtBonnie Doon, Edmonton · 21 units | Assisted living | under 1 km | 100%1 of 1 visit |
| Ted Bradshaw HomeBonnie Doon, Edmonton · 10 units | Group home | under 1 km | 100%2 of 2 visits |
| L'Arche Noah HouseKing Edward Park, Edmonton · 6 units | Group home | under 1 km | 67%2 of 3 visits |
| Saint Thomas Health Centre / Centre De SantÉ Saint-Thomas - Covenant CareBonnie Doon, Edmonton · 141 units | Type B (designated supportive living) | 1.1 km | 71%5 of 7 visits |
| Extendicare Holyrood (South)Holyrood, Edmonton · 74 units | Long-term care (Type A) | 1.6 km | 100%3 of 3 visits |
Check the government’s record
Inspections are a snapshot. Visit, ask for the home’s latest inspection report, and ask the questions above. Concerns about a specific visit go to the home first, then to the Continuing Care Licensing Office (cclo@gov.ab.ca).
Source: Government of Alberta, Continuing Care Accommodation Standards compliance reporting on Open Alberta (Open Government Licence – Alberta), file of —, with visits to July 6, 2026. Results are as the government recorded them. An inspection is a snapshot. The official record and the finding text are on the government’s viewer; the dates and statuses here come from the file. How this is built.